Foundry

Sector: Metallurgy
The project

The project consisted of the installation of 2 Big-bag stations with 2 transfer systems equipped with buffer hoppers at ground distances of 5 meters and elevations of 1.50 and 2 metres.

The transfer protocol required a dosage for one of the products.

What was the response?
  • 2 Big-bag stations
  • A T52 system consisting of a 200 L hopper and a T54 dosing system
  • A Transitube T51, with an unscrewing system, for the transfer of the second product - clogging agent